PDMS Project Transfer without using Aveva global

 
  • I have been using global for the existing Project but for new project its a new client which doesnt have any experience on global so he wants to use ftp transfer for transfering the project and later on change it to global if need.
    The pdms model is built at both end partially so there will be transfer of dB every weekend.
    few question on the above topic.
    1. Is it ok to change the project into Global in mid of the project.
    2. While transfering the Project files how important are the sys,com & mis files