PDMS "Lessons Learned"
Troubleshooting PDMS Project Version Upgrade
  • Forums
  • Resources
  • Mentions
  • Sub-Groups
  • Tags
  • More
  • Cancel
  • New
  • Replies 25 replies
  • Subscribers 1 subscriber
  • Views 64 views
  • Users 0 members are here
Options
  • Share
  • More
  • Cancel
Related

PDMS Project Version Upgrade

Srinivas K
Srinivas K over 12 years ago
 
  • Sign in to reply
  • Cancel
  • Parag S Newe
    Parag S Newe over 12 years ago
    but also full project(dabacon bases). And he requires the same version as he use...



    ok.. so what is procedure for Downgrade project?
    • Cancel
    • Vote Up 0 Vote Down
    • Sign in to reply
    • Cancel
  • me_hungry
    me_hungry over 12 years ago
    Hi RUAV,[COLOR=#000000] can U give manuals for this procedure or give a link where it can found?!

    Thanks :)[/COLOR]
    [COLOR=#3E3E3E][/COLOR]
    • Cancel
    • Vote Up 0 Vote Down
    • Sign in to reply
    • Cancel
  • Corrado Galluzzi
    Corrado Galluzzi over 12 years ago
    thanks all of you      is it possible to downgrade the project?


    Could you please explain why you need to downgrade a project?

    AVEVA......Continual Progression!!!! :-)
    • Cancel
    • Vote Up 0 Vote Down
    • Sign in to reply
    • Cancel
  • Nguyen Hong Anh
    Nguyen Hong Anh over 12 years ago
    [QUOTE=corrado;75633]Could you please explain why you need to downgrade a project?

    AVEVA......Continual Progression!!!! :-)
    Dear corrado. you can see reason about that in here:
    http://52.178.132.139/showthread.php?t=13558

    My company has just  more 3 licences PDMS 12.1 version. This version possible to downgrade. Kindly give some advices.
    • Cancel
    • Vote Up 0 Vote Down
    • Sign in to reply
    • Cancel
  • Corrado Galluzzi
    Corrado Galluzzi over 12 years ago
    Dear corrado. you can see reason about that in here:
    http://52.178.132.139...ad.php?t=13558



    I know I am asking an obvious question....

    ....but why your company has not agreed with the client which PDMS version should have to be used before starting the project?
    • Cancel
    • Vote Up 0 Vote Down
    • Sign in to reply
    • Cancel
  • Corrado Galluzzi
    Corrado Galluzzi over 12 years ago
    http://52.178.132.139/showthread.php?t=13137
    • Cancel
    • Vote Up 0 Vote Down
    • Sign in to reply
    • Cancel
  • Corrado Galluzzi
    Corrado Galluzzi over 12 years ago
    You can also read C:\AVEVA\Plant\PDMS12.0.SP6\Manuals\Docs\PDMS User Bulletin12.0.pdf Chapter 4.6.3 Passwords

    So...I suggest you to contact your nearest Aveva Office... :-)
    • Cancel
    • Vote Up 0 Vote Down
    • Sign in to reply
    • Cancel
  • Nguyen Hong Anh
    Nguyen Hong Anh over 12 years ago
    [QUOTE=corrado;75796]I know I am asking an obvious question....

    ....but why your company has not agreed with the client which PDMS version should have to be used before starting the project?
    This is not my scope of work corrado :)...but in my opinion Vendor always try to meet any requirements from client LOL.
    As u know, autocad, microsoft office and many softwares can be downgrade...why does PDMS try to do that? it's so convinient for user.
    • Cancel
    • Vote Up 0 Vote Down
    • Sign in to reply
    • Cancel
  • me_hungry
    me_hungry over 10 years ago
    Is it possible to rollback fix update, from 12.1.2.33 to 12.1.2.30 ?
    • Cancel
    • Vote Up 0 Vote Down
    • Sign in to reply
    • Cancel
  • Corrado Galluzzi
    Corrado Galluzzi over 10 years ago
    I think you need to uninstall no.33 and ask Aveva for no.30
    On the Aveva Support Website you only have the latest fix.