Plenty of threads about this matter!
Anyway you can read C:\AVEVA\Plant\PDMS12.0.SP6\Manuals\Docs\PDMS User Bulletin12.0.pdf Chapter 2.5 Upgrading from PDMS 11.
In particular Chapter 2.5.2 Performing the upgrade process
' UPGRADE PROJECT TO LATEST '
As far as I know the correct syntax is DBUP PROJECT TO LATEST.
This is for upgrading from 12.0 to 12.1 as explained in the 12.1 PDMS User Bullettin
I read the manual, still I need a help to follow the step by Step, if anybody have macro please share ...
This comes from the manual:
If the project is not Global, the process is very simple[/U]. The upgrade is initiated by running the
upgradeMac macro from the Monitor command window, either by typing:
$m/C:\AVEVA\plant\PDMS12.0.SP6\pdmsui\dra\upgrade\upgradeMac
or by dropping the upgradeMac macro on to the command pane.
That's just a list of tasks that the upgrade process performs.
You do not need to do anything apart (eventually) updating the spatial map.
You can find answers to your questions in the PDMS 12 or 12.1 User Bullettin and in the Admin manuals.
I would strongly recommend you to attend a PDMS Admin Training Course.
Haha)) When customer orders pdms project, not only [COLOR=#008000]rvm+att+isometric+reports[/COLOR] but also full project(dabacon bases). And he requires the same version as he use...